Polypipe Civils & Green Urbanisation [Polypipe CGU] worked closely with Balfour Beatty to provide a solution using its Polystorm and Polystorm Xtra modular cells, creating four separate soakaway structures.

With the first two – relatively simple – structures installed in November 2008, in-depth design work then began on the third and fourth soakaway applications.

Polypipe CGU was heavily involved in the design process, alongside Balfour Beatty and consultant engineers Mott Macdonlad and Atkins.

A3 circular Polystorm installation 3 - WEB.jpg

The innovative solution designed by Polypipe CGU in conjunction with Balfour Beatty used Polystorm cells installed in a circular, concrete-lined tank. Granular material was then used to fill the gaps and maximise the performance of the soakaway. A 1500mm catchpit was also used to divert excess stormwater to the soakaway structure. Polystorm and Polystorm Xtra cells were used to form the fourth structure, creating a six metre wide by 62 metre long structure. Polystorm Xtra cells formed the base layer of the soakaway tank to achieve an installed depth of 4.2 metres. Working closely with Balfour Beatty, Mott Macdonald and Atkins, a number of 750mm diameter ‘wicks’ were designed using a 750mm collar and structured-wall pipe with a gravel filling. This provides a 30% void ratio and improves the flow of surface water from the soakaway structure down to the permeable soil strata at 15 metres.

Daniel Machnik, Senior Buyer for Balfour Beatty Civil Engineering, was impressed with the innovative water management solution provided by Polypipe CGU, saying: “The adaptability of the Polystorm and Polystorm Xtra cells offered an advantage on this challenging scheme, and the installation guidance the team has demonstrated on site has been of great value.”

Polystorm - Roads - Soakaway - A3 - Image 20.jpg

Polypipe CGU also undertook further design work for £200,000 worth of cable protection products supplied for the project. To improve the installation times of the cable protection within a tunnel section of the project, Polypipe CGU suggested a large bank of sealed ducts in 94 and 150mm diameters to be installed using its 150mm Ridgidrain pipe with integral sockets.

As part of an overall commitment to reducing its impact on the environment, Polypipe CGU also implemented a recycling scheme on site, collecting off-cuts of pipe for re-use in its manufacturing process.