Work began on the project in 2025, with Hannon Brothers Ltd appointed to undertake the groundworks for Unit 4 of the development: a 545,000 square foot warehouse.
“We started this project in June,” Mark Jackson, Contracts Manager at Hannon Brothers Ltd, said, “and it includes a drainage scheme where it’s attenuated drainage with around 600 metres of 1500 diameter pipework to install, with a further 1,200 metres worth of associated drainage connections off that. At the beginning of the project, our discussions with Lee [Woodcock, Key Account Manager at Polypipe Civils & Green Urbanisation] ramped up and we started to discuss potentially using pre-formed chambers. It was an absolutely brilliant start to the project and, having weighed up the pros and cons between plastic and traditional materials, it became clear that the speed of the installation of Polypipe CGU’s chambers would outweigh any material costs, so that’s the solution we chose, and it saved us a world of pain compared to constructing traditionally.”